.17801cfa.webp&w=3840&q=75)
 Projects 
Lebanese Ministry of Interior, Substructure for New Building, Beirut Central District
Beirut, Lebanon
Project Type(s): Offices
Construction of 6 levels of underground parkings, with a total built-up area of 19,000 m². Works included major reinforced concrete works totaling 20,000 m³, raft foundation of 4,000 m³, and suspended transfer slab (160 cm thick) at first basement level.
Status: Completed 2000
Employer:
The Lebanese Company for the Development and Reconstruction of Beirut Central District S.A.L. (SOLIDERE)
Consultants:
Syrconsult Consulting Engineers