.17801cfa.webp&w=3840&q=75)
 Projects 
Charles Hélou Multi-Level Bus Terminal Construction, Beirut East Entrance
Beirut, Lebanon
Project Type(s): Roads & Bridges
Construction of multi-level bus terminal comprising: 450-meter-long & 37-meter-wide 3-story building, foundations on diaphragm wall (barrettes) excavated and cast under bentonite, pre-stressed & precast beams for the roofs, 2 floors used as car parks, ground floor used as bus terminal, upper deck used as motorway, 2 pre-stressed concrete access bridges (52 m and 50 m span), access roads to all floors & connection to neighboring streets.
Status: Completed 1973
Employer:
Conseil Exécutif des Grands Projets de la Ville de Beyrouth (C.E.G.P.V.B.)
Consultants:
Gicome (Antoine Salamé & Associés S.A.R.L.)